The HDS Installation Revamping

The HDS Installation Revamping

As part of the Euro5 Project, we executed lifitng operations and pipeline works for the new HDS installation:

  • Loading the columns stored in the refinery’s warehouse on trailers
  • Identifying the best transportation route inside the refinery.
  • Lifting and erection of 2 columns measuring 23 m high and weighing 26 tons each
  • Erection of heat exchanger
  • Fabrication and mounting 1100 linear metres of pipelines