Closed Blowdown System for Delayed Coker Unit ( DCU)

Type of Activity: General Contracting (GC) / New Unit Construction

Sector: Oil & Gas, Petrochemicals

Client: Lukoil

Country: Romania

Period: 2021

As part of the Closed Blowdown System for Delayed Coker Unit (DCU) project and in its capacity as General Contractor (GC), Industrial Montaj was responsible for and carried out:

  • Procurement and supply chain management.
  • Project management, planning under Primavera, safety, and waste management on-site.
  • Civil engineering and demolition work (2,900 m³ of excavation / 90 tons of reinforcement steel / 910 m³ of poured concrete).
  • Prefabrication and installation of 340 tons of steel structures, including the reinforcement of an existing structure.
  • Lifting and installation of equipment (14 pieces totaling 483 tons).
  • Prefabrication and installation of 20,000 inches of piping (180 tons) – carbon steel, alloy, and stainless steel.
  • Electrical & instrumentation work, including electric tracing.
  • Scaffolding management, insulation work, and handling of lifting equipment.