SKID Erection and process piping

Contract Type: General Contractor

Sector: Cosmetics

Client: Procter & Gamble

Location: Romania

Period: 2017

As part of a production capacity increase, Industrial Montaj carried out the installation of new process/skid equipment.

The particularity of this project lies in the special execution conditions within a manufacturing area subject to GMP regulations, with the possibility of working outside production periods.

The Industrial Montaj teams were responsible for:

  • Detailed (3D) engineering for the positioning of skids and connection piping
  • Procurement management
  • Manufacturing and assembly of a 35-ton metal structure
  • Prefabrication and installation of connection piping for the equipment (2.2 km, including process piping welded using orbital welding)
  • Preparation and execution of installation operations for 6 skids + 1 tank with a capacity of 150 tons
  • Execution of civil engineering works
  • Electrical wiring and instrumentation works
  • Line passivation by recirculation
  • Thermal insulation
  • Commissioning & start-up assistance