Activity Type: General Contractor (GMC) / Intermediate Shutdown
Sector: Oil & Gas, Petrochemicals
Client: Lukoil
Country: Romania - Petrotel Ploiesti
Period: 2023
The Industrial Montaj teams prepared and carried out the 2023 Intermediate Shutdown (20 days) for all pressure equipment across the refinery units.
As a General Contractor, our teams completed:
- Preparation of operating procedures & Project Management
- Planning using Primavera
- Assistance with the commissioning of units for 18 units
- Opening / closing of equipment
- Metallurgical repairs on equipment (90 interventions)
- Pressure testing for equipment
- Assistance for start-up for 18 units
- On-site machining and rectification
Additional Info:
A 100% digitalized management system for progress tracking during the shutdown using our activity tracking system via QR codes.
Some equipment figures:
- Columns: 34 units
- Heat exchangers: 166 units
- Reactors: 6 units
- Pressure vessels: 133 units
- Furnaces: 19 units
- Aerators: 68 units