Turnaround 2023 OMV Petrom Romania

Contract Type: General Mechanical Contractor

Sector: Oil & Gas

Client: OMV Petrom

Location: Romania – Petrobrazi

Period: 2023

For its 2023 Major Turnaround (45 days), OMV Petrom entrusted Industrial Montaj with the preparation and execution of the turnaround for the following units:

  • Cogeneration & Utilities
  • Tank Farm
  • RC2 – Catalytic Reforming

Scope of Work:

  • Technical preparation and planning (Technical audit, resource sizing, scheduling under Primavera – 12,000 activities)
  • Preparation of intervention documents & work packages
  • Maintenance works on equipment and piping
  • Metallurgical works on equipment
  • Repairs on piping systems
  • Primavera schedule updates throughout all shutdown phases
  • Coordination of auxiliary activities (Extraction, Scaffolding, Crane & Lifting Equipment, Insulation)

Key Figures:

  • Aerators: 17 units
  • Heat Exchangers: 90 units
  • Columns: 6 units
  • Reactor: 1 unit
  • Damper: 175 units
  • Tanks: 34 units
  • Flue stacks: 6 units
  • Furnaces: 3 units
  • Boilers: 7 units
  • Piping Repair Project: 199 welding points
  • Pressure tests for 1,413 pipelines registered with local authorities (ISCIR)
  • Total inches welded: 11,500 inches

Special Works:

  • Replacement of 3 flare tips
  • Replacement of DN1000 flare line
  • Intervention on 120-bar heat exchangers
  • Over 50 different welding procedures used during the turnaround

Industrial Montaj is proud to have successfully delivered this critical turnaround, ensuring efficiency and safety at the Petrobrazi refinery!