Activity Type: General Contractor / Major Turnaround
Sector: Oil & Gas, Petrochemicals
Client: KMG - Rompetrol
Country: Romania – Petromidia
Period: 2024
The Industrial Montaj teams successfully took on the challenge of executing the 2024 Major Turnaround (45 Days) for the following three units:
- Fluid Catalytic Cracking (FCC)
- Mild Hydrocracking (MHC) – Steam Cracker
- Middle Distillate Hydrotreating (HDV)
Scope of Work:
- Unit handover assistance
- Disassembly and reassembly of 250 valves & safety relief valves
- Execution of 151 piping repair projects (151 welding points)
- Piping discovery works: 128 interventions
- Metallurgical repairs on equipment (113 interventions), including the replacement of a shell section on a column
- Post-weld heat treatment (PWHT)
- Pressure testing for 490 pipelines registered with local authorities
- Pressure testing for equipment
- Assistance for start-up
- Installation of two new reactors
- On-site machining and grinding
Material Grades Handled:
16Mo3, Gr. P11, P22, P5, 304L, 304H, 310, 316L, 321, 347, 410, Alloy 800H
Key Project Highlights:
- 100% digitalized turnaround management using our QR code-based activity tracking system
Special Works:
- Replacement of a shell section on a column, including the removal of the column head for installation of the new shell section
- Replacement of the expansion joint between the Regenerator & the Plenum Chamber on the FCC unit
Key Equipment Figures:
- Columns: 16 units
- Heat Exchangers: 83 units
- Reactors: 6 units
- Damper: 61 units
- Furnaces: 5 units
- Aerators: 70 units
- Over 6,000 inches of welding completed during the turnaround
- Replacement of a shell section on a column